Guide · Updated 2026-10-02
How to Track Client-Specific Inductions
Client-specific inductions expire when the site, contract or briefing cycle says they do. Put each induction on its own matrix column or requirement, copy the completion date from the register or LMS, and attach the signed evidence. A company induction does not cover a principal-contractor site brief.
Quick answer
Name the induction after the client or project — for example “ACME Gateway PC induction” — not a generic “Site induction”. Record who completed it, when, and where the proof lives. When the project ends or the client reissues the brief, close or renew that column. Do not leave a green cell implying lifelong access. Structure this beside portable tickets using a role-based training matrix and keep evidence searchable with training matrix software when Excel filters stall.
One induction, one requirement
Client inductions fail when three different sites share one column labelled “Inducted”. A worker who completed Client A’s e-learning last year looks cleared for Client B’s gate this Monday. Separate company induction from every principal-contractor or client brief, and add project codes when the same client runs several live sites.
- Separate company induction from client / PC inductions
- Add project codes when the same client runs several live sites
- Store e-learning certificates and signed attendance sheets against the same requirement
- Note whether the induction is time-limited or project-limited
- Record the briefing version or pack date if the client reissues content mid-contract
Ownership on busy programmes
| Role | Owns | Hands off when |
|---|---|---|
| Commercial / bid | Which clients demand a unique induction | Contract signed and rule written |
| Site or project admin | Register, LMS bookings, day-one completions | Evidence attached same day |
| Matrix owner | Column naming, dates, Monday filters | Deputy named for leave weeks |
| Supervisor | Stops work if gate rejects missing induction | Escalates — does not invent a green cell |
Weekly control without drowning in columns
You do not need every historic site as an active column forever. Keep active project inductions on the live matrix. Archive finished-site columns after demobilisation so filters stay usable — see how to archive completed site columns. Filter by project before Monday mobilisation rather than scrolling a wall of old greens.
Step-by-step setup
- List live clients and projects that require a unique induction.
- Create one matrix requirement per induction rule with a clear name.
- Import or enter completion dates from the register or LMS export.
- Attach evidence the same day the briefing is signed or completed online.
- Tag workers to the projects they may attend this week.
- Test a Monday filter for one site before you scale the pattern.
- Archive the column when the site closes; keep evidence for retention.
Failure modes
- One “Site induction — Yes” cell reused across every client
- Company induction treated as proof of PC site brief
- LMS completion email never filed against the matrix requirement
- Green status left after the client reissues a new induction pack
- Agency workers arriving with “done on another job” and no evidence
Example: two warehouses, one client brand
Client ACME runs Site North and Site South with different principal contractors. You create ACME-North-PC-induction and ACME-South-PC-induction. A steel erector cleared for North still shows a gap for South until that brief is done. Monday’s gang for South filters on the South column only. Evidence filenames include the site code so auditors do not mix packs. Retention after close follows how long to keep site induction records.
HSE and product context
Inductions support safe access and local rules; they do not replace task training. Use HSE material when shaping what your own company induction must cover, then track client packs separately. A training matrix template with named induction columns is enough for small programmes; multi-site filters usually need software.
Honest limits
FieldClear tracks the induction requirements you assign. It does not decide which client inductions a site demands, deliver the briefing content, or certify that someone is ready for work. This is operational guidance, not legal advice.
Free download
Need a training matrix template?
Download our free Construction Training Matrix Excel template. Worker rows, requirement columns, expiry dates and conditional formatting already set up.
Already have one?
Turn your spreadsheet into a live matrix with automatic expiry reminders.
Upload my matrixtraining-matrix-template.xlsx
| Row number | A | B | C | D | E | F | G |
|---|---|---|---|---|---|---|---|
| 1 | Name | Role | CSCS | IPAF | PASMA | First Aid | Asbestos |
| 2 | Ahmed Khan | HVAC Engineer | 12/08/2028 | 25/08/2026 | 03/02/2028 | 19/09/2027 | — |
| 3 | John Smith | Site Supervisor | 04/06/2029 | 22/01/2028 | 18/09/2026 | 18/09/2026 | 11/11/2027 |
| 4 | Sarah Jones | Electrician | 28/10/2028 | 16/05/2028 | 16/05/2028 | 02/12/2027 | 09/07/2028 |
| 5 | Peter Brown | General Operative | 06/08/2026 | 14/04/2028 | — | — | 21/01/2028 |
| 6 | Grace Okafor | Electrician | 17/03/2029 | 27/09/2026 | 08/08/2028 | 23/06/2028 | 05/05/2028 |