Guide · Updated 2026-10-02
How to Review a Training Matrix Before Monday Mobilisation
Review the matrix against the people who will actually travel — not the whole company. Filter the project or gang, ignore noise from N/R cells, chase critical gaps, and publish a clear go/no-go list before Monday. The review is a short operating rhythm, not a monthly report.
Quick answer
By Friday afternoon (or Sunday for night shifts), filter to Monday’s gangs, list true gaps, update the gap log, and confirm substitutes for anyone still blocked. Do not wait until the gate. Use project or gang filters every time.
Review agenda (30–45 minutes)
- Confirm travelling names with supervisors — capture late swaps.
- Filter matrix to those people and sites.
- Check portable expiries and client inductions for those sites.
- Separate Booked from Complete — booked tracking.
- Verify last-minute subcontractor/agency CSCS where needed.
- Update gap log actions.
- Publish go/no-go list to supervisors and gate contacts.
Who must be in the room (or on the call)
| Role | Why |
|---|---|
| Matrix owner | Runs filters and evidence checks |
| Supervisor / ganger | Confirms who travels |
| Training coordinator | Owns bookings and chases |
| PM (if gaps threaten programme) | Approves substitutes or delays |
What “good” looks like before vans leave
- Every travelling person is Active with correct tags
- No expired critical tickets without a substitute plan
- Client induction present for the destination site
- Evidence links open for a sample of cleared people
- Gap log shows owners for anything still open
Failure modes
- Reviewing Friday’s plan while Saturday swaps are ignored
- Treating Booked as Cleared
- Only checking CSCS and skipping site induction columns
- No published go/no-go — each supervisor invents a list
- Screenshot of the whole matrix emailed with no filter
Example: three gangs, one shared matrix
Friday 14:00 review runs three filters. Gang A clear. Gang B missing one PC induction — booked Monday 06:30 on site, so they travel only if the gate allows induction-first; otherwise substitute. Gang C has an agency no-card risk; replacement pre-cleared via CSCS verification. Go/no-go list hits WhatsApp and email by 15:30.
HSE and product
Pre-mobilisation checks keep unsuitable people off tasks. Align with how you manage work under HSE. Training matrix software speeds filters and evidence opens; a training matrix template works only if the review actually happens.
Privacy
Go/no-go lists name people and sometimes reasons. Send to those who need them, retain briefly, and follow ICO principles — do not post full matrices in public channels.
Cut-off times that make the review real
Publish a cut-off: for example, name list locked 14:00 Friday, evidence cut-off 12:00 Friday for agency packs, review at 14:30. Late swaps after cut-off need an exception path with the same checks condensed — not a shrug. Night-shift and weekend works need their own clock. Without cut-offs, the review becomes theatre while vans load whoever arrived.
- Put cut-offs on the mobilisation checklist
- Measure exceptions weekly — too many means the cut-off is ignored
- Keep a short standby list of pre-cleared people for critical trades
- Align gate staff to the published go/no-go list only
Pre-flight checklist (print or pin)
- Filter to Monday’s projects and gangs only.
- List red/amber cells that block those people.
- Separate Booked from Complete — booked is not cleared.
- Confirm agency and subcontractor rows have attachments.
- Agree replacements or scope cuts before vans are loaded.
- Publish the cleared list to supervisors in one message.
Honest limits
FieldClear shows current statuses and evidence. It does not replace the supervisor’s final decision at the gate. Not legal advice.
Already have a spreadsheet?
Upload your existing matrix and see who’s current, what’s expiring and what’s missing.
14-day free trial. No card required.